Milestone 3
- Group 7
- Apr 16, 2019
- 1 min read
Updated: Apr 19, 2019
Objectives:
Update/fix any issues found during milestone #2
Complete web application and present a working prototype
Complete all required documentation
Begin preparing for C-Day presentations
Complete C-Day poster, PowerPoint and final report
Test web app functionality
Collect all project related files and prepare them for submission
Activities:
Completed installation and configuration document
Completed Gantt chart
Completed final project report document
Completed web application prototype
Began preparing for upcoming presentations (C-Day)
Prepared and submitted all project files in the requested format
Events:
Held 1-2 hours group meetings each week
Practiced presentation of poster, PowerPoint, and web app prototype
Achievements:
Requirements and documentation all submitted on time
Effective communication among group members
Challenges:
Dynamic PHP project page creation (resolved)