Milestone 1
- Group 7
- Apr 16, 2019
- 1 min read
Updated: Apr 19, 2019
Objectives:
Begin creating GUI
Set up database
Complete user requirements document
Complete milestone #1 PowerPoint presentation
Activities:
All page wireframes created
Development of GUI and database
Updated Gantt chart each week
Completed milestone #1 PowerPoint
Events:
Milestone #1 presentation and meeting with sponsor and advisor
Held 1-2 hours group meetings each week
Achievements:
Requirements and documentation all submitted on time
Effective communication among group members
Combined 46 hours of work completed
Challenges:
Virtual machine creation delayed project until it was complete
Comments