Milestone 2

  • Group 7
  • Apr 16, 2019
  • 1 min read

Updated: Apr 19, 2019

Objectives:

Update/fix any issues found during milestone #1

Continue web app development

Complete web app design document

Complete milestone #2 PowerPoint presentation

Activities:

Continued development of GUI and database

Completed web app design document

Updated Gantt chart each week

Events:

Milestone #2 presentation and meeting with sponsor and advisor

Held 1-2 hours group meetings each week

Achievements:

Requirements and documentation all submitted on time

Effective communication among group members

Combined 60 hours of work completed

Challenges:

Some misunderstanding of requirements between group and sponsor (resolved)

 
 
 

Recent Posts

See All
Milestone 3

Objectives: Update/fix any issues found during milestone #2 Complete web application and present a working prototype Complete all...

 
 
 
Milestone 1

Objectives: Begin creating GUI Set up database Complete user requirements document Complete milestone #1 PowerPoint presentation...

 
 
 

Comments


©2019 by IT Capstone - Progress Tracking.

bottom of page